Three phase reconstruction where works commenced around a working hospital.
- Phase 1 - 45 weeks
- Phase 2 - 45 Weeks
- Phase 3 - 16 Weeks
Substructure:
- Basement slab
- Ground floor slabs in reinforced concrete
- Retaining walls
Superstructure:
- In situ reinforced concrete slab
- Ground, first and second floor 400mm think slabs
- In situ reinforced concrete columns
Mitchellson also provided the steel framed plant room roof structure and independent steel framed structure with composite concrete floors on metal decking for the FM yard building.